Project Overview

Stafford County retained Total Stormwater Solutions to develop a comprehensive county-wide stormwater master plan to guide capital investment over the next 50 years. The project included GIS-based asset inventory, condition assessment of 2,000+ structures, hydraulic modeling of the county drainage network, and a prioritized capital improvement program with cost estimates.

Scope of Work

  • GIS-based inventory of 2,000+ stormwater structures
  • Field condition assessment using standardized scoring
  • Hydraulic modeling of county primary drainage network
  • Problem area identification and flood risk mapping
  • Capital improvement project identification and prioritization
  • 50-year CIP development with cost estimating
  • GIS asset management database configuration
  • County council presentation and public outreach support

Results

  • $15M in prioritized capital improvement projects identified
  • 50-year infrastructure investment roadmap adopted by county
  • GIS asset management system operational with 2,000+ records
  • Three emergency repair projects fast-tracked from findings